Project Description

Securus Data Property Fund Pty Ltd (Securus) engaged FDC Construction & Fitout to complete the internal fitout to the balance of the base building, which was constructed by FDC in 2011.

Due to the extreme program restrictions, Securus approached FDC as both the base building contractor and an accredited and award winning contractor specialising in Data Centre construction.

This project was completed in a record time of six months. The project commenced January 2012 and was fully commissioned and operational for an early access tenant as of May 2012, with full practical completion achieved in July of that year; making it the fastest data centre construction in Australia for this amount of white space and reliant services.

Project Features

  • Four data halls
  • Plant space with DRUP units, chillers and generators
  • Fully commissioned and operational within 6 months

Project Size

3,200sqm

Program

24 weeks

Client

Securus